SACRED HEART SCHOOL

Client

Hoffman & Associates

Project Lead

Mary Ann McBee, Playground Specialist 

Project Overview

This project involves complete site preparation, high-quality poured-in-place surfacing, and the installation of new playground equipment, ensuring a safe, durable, and visually appealing play environment. All aspects of the work are conducted with professional care and attention to detail.

Scope of Work

Mulch and Dirt Removal

  • Removal of 8-10 inches of mulch and dirt across approximately 7,800 square feet
  • Estimated volume: 273 tons (196 cubic yards)
  • Includes all labor, materials, and dump fees

Base Preparation

  • Install 5-6 inches of Class 2 base over 7,800 square feet
  • Estimated volume: 170 tons (120 cubic yards)
  • Includes compaction of 90-95% every 4 inches, ensuring a stable foundation
  • All labor materials , and freight included

Poured-in-Place (PIP) Rubber Surfacing

  • Install 3 1/2 inches of PIP surfacing 
  • Color Mix: 50% standard color (Blue, Green, Red, or Beige) and 50% Black with aromatic binder
  • Includes all labor, materials, and freight

New Equipment Installation

  • Provide and install a new balance beam, ensuring proper alignment and safety compliance